Construction blog
Menu

To vedbil.se

Guest book

Contact

Travel blog

Blog start

Day 58 Sw
Day 57 Sw
Day 56 Sw
Day 55 Sw
Day 54 Sw
Day 53 Sw
Day 52 Sw
Day 51 Sw
Day 50
Day 49
Day 48
Day 47
Day 46 Sw
Day 45 Sw
Day 44 Sw
Day 43 Sw
Day 42 Sw
Day 41 Sw
Day 40
Day 39
Day 38
Day 37
Day 36
Day 35
Day 34
Day 33
Day 32
Day 31
Day 30
Day 29
Day 28
Day 27
Day 26
Day 25
Day 24
Day 23
Day 22
Day 21
Day 20
Day 19
Day 18
Day 17
Day 16
Day 15
Day 14
Day 13
Day 12
Day 11
Day 10
Day 9
Day 8
Day 7
Day 6
Day 5
Day 4
Day 3
Day 2
Day 1
 

Day 2 31/12 2006

Today we have started to build the gas cooler and destroyed a oil tank that we are going to use the material from. The gas cooler consists of two horizontal 3” pipes with twelve 1” cooling pipes connecting them together. We will put a tank beneath the cooler to collect condensate water. We will also make a connection for the starting fan. Our hole saw was to week fore the 3” pipes, so we had to mill the holes. That was no problem for Martin, but he killed one drilling machine. Now we only have to weld the construction together.

The oil tank consists of 3 mm sheet metal. Vi crosscut the tank so we got the welded corners. That saved us a lot of time. We then sat down and discussed the construction and we came up with the idea to build the cyclone filter in to the fine filter. This will make the gases from the generator going in the cyclone heating up the fine filter.

Now we are going to take the evening of to celebrate New year’s eve!

 

 